Loaning Resources to Other Worlds
The following example shows a WebAdmin administrator of a North Belfast World loaning a Resource to a South Belfast World for an afternoon (four hours):
-
In WebAdmin, select Optimise Schedule.
-
The Worlds window appears. Select a World.
-
The Optimise Schedule window appears. Resource Simon Graham has four hours of unused Availability in the afternoon:
Select Loan Availability
. -
The Loan Availability window appears:
-
To filter the Resources select in the Search field and type a Resource name.
Select the Select All icon
, or the Deselect All icon
.Or select individual Resources for loaning.
-
Select in the World Reference field and select a World from the dropdown.
-
Select in the Reason field and select a Reason from the dropdown.
-
Enter a Description.
-
Enter a Start Date/Time of the loan Availability.
-
Enter a End Date/Time of the loan Availability.
-
Select Save Loan Details.
-
The North Belfast World Optimise Schedule window updates and shows the Unavailability of the Resource within the World:
When you manually refresh the South Belfast World Optimise Schedule window the loaned Availability of the Resource displays within the World. You/Mendel can schedule the Resource Jobs within the available time: