Pinning Jobs to a Date and Resource

To pin a job to a date and resource for any time:

  1. In WebAdmin select Optimise Schedule.

    The Worlds page appears.

  2. Select a World.

    The Optimise Schedule page appears.

  3. To adjust the date, select the arrows on the calendar.

    Alternatively, select the current date to display the calendar, then select a date within the calendar to set the Diary to that day.

  4. In the Job List, select a job and drag it to the bottom area of a resource card.

    The area changes to a green colour.

  5. Drop the job onto the resource card.

Removing Pinned Jobs from a Date and Resource

  1. In WebAdmin select Optimise Schedule.

    The Worlds page appears.

  2. Select a World.

    The Optimise Schedule page appears.

  3. To view the jobs pinned against a resource, select the Pin icon.

    The Pin Information dialog for the resource appears.

  4. To unpin the job from the resource select Remove Pin.